Tender Description
The project consists of doing bank works for Wesley College Boat Landing Facility. The scope to be delivered includes, but is not limited to the supply of material, plant,
labour necessary to carry out the following:
- Earthworks and stabilisation piles
- DDA compliant pathway
- Carparking and pavement works
- Stormwater drainage
- Landscaping including hardscape and planting
Trades Involved
03 - Civil/Ext Works
- Asphalt
- Civil - Kerb & Channel
- Civil Contractor
- Concretor - External Works
- Gabion Walls
- Pavement - Permeable
- Stormwater Drainage
04 - Structure
- Bored Piers
- Piling - CFA / Contiguous
- Piling - Screw Piles
09 - Landscape/Civic